Hoppa till innehållet

Valpene Wind

Valpene is a place in the Dundaga Parish of Talsi Municipality. Valpene has excellent wind conditions, making it an ideal location for wind farm development.

Type

Onshore wind power

Phase

Planning

Market

Latvia

Annual electricity production

800 GWh

Quick facts

Name

Valpene Wind

Number of units

34

Project area

25 km2

Total unit height

250m

Planned COD

2028

About the Project

The Valpene wind power farm will be Eolus largest onshore wind farm in Latvia, with plans to produce up to 800 GWh annually, significantly contributing to Latvia’s energy independence.

 

Project Development Timeline:

  • On 19 June 2026, a grid connection agreement was signed with AST, securing the reservation of grid capacity for the implementation of the project. The grid capacity reservation status is available here.
  • In Q4 2025, the initial geotechnical investigation of the project site was completed, and the necessary data were prepared for further design and engineering activities.
  • On 22 August 2025, an agreement was concluded with AST for the establishment of a new connection to the electricity transmission system.
  • On 7 March 2025, the Energy and Environment Agency (EVA) issued a permit for the installation of new electricity generation facilities.On December 2, 2024, the State Environmental Service issued a positive opinion on the Environmental Impact Assessment (EIA) report for the Valpene Wind Farm. See here.
  • On November 11, 2024, the Ministry of Environmental Protection and Regional Development (VARAM) approved the local spatial planning for the wind farm’s construction.
  • In September 2024, two meteorological masts were installed in Valpene to measure wind speed and direction.
  • In September 2024, two wind measurement masts were installed in the Valpene Wind Park research area and commissioned in October.
  • On August 29, 2024, the Talsi Municipality Council issued binding regulation No. 21, covering the local spatial planning for the Valpene Wind Farm, including land use and construction regulations, as well as the graphical section. See here.
  • In February 2024, a public consultation happened for the Environmental Impact Assessment and local spatial planning.
  • In January 2024, the Latvian Investment and Development Agency granted the project the “green corridor” status.
  • In November 2023, a SODAR wind measurement system was installed in the territory.
  • In October and November 2023, two working group meetings were held to discuss the wind farm’s environmental impact and its effects on public health and safety.
  • In June 2022, the Talsi Municipality Council decided to begin drafting the local spatial plan. See here.
  • In January 2022, the State Environmental Service issued the program. See here.
  • On July 9, 2021, The Environmental Impact Assessment (EIA) process has been launched. See here.

 

The development of the hybrid park concept, preparation of technical documentation, and the processes required to commence construction are currently underway.

Pictures from the Project

Choose market

Global

  • Svenska
  • English
  • Local

  • Suomi
  • Polski
  • Latviešu
  • North America